London Luton Airport (LTN) in the UK has completed a significant £18 million investment in resurfacing its runway.

The investment to upgrade the durability and performance of the runway ensures the continued long-term safety and efficiency of airport operations from a regulatory and safety viewpoint.

The complex project was delivered over five months of night working by a 120-strong team of resurfacing experts, following months of meticulous planning to ensure operational impacts were kept to a minimum level.

Work on the 2.16 kilometre runway commenced each night at 00:01 and completed by 05:45 ahead of the first scheduled flight to depart.

Each nightshift involved more than 120 plant and vehicles, and required detailed planning with airfield operations, Air Traffic Control and teams across the airport including health and safety, motor transport, technical engineering services and security.

Infrastructure director at London Luton Airport, Marc Wolman, commented: “The resurfacing of the London Luton Airport runway was an immense, once in a generation project – the airport’s largest airfield engineering programme in two decades.

“A complex project of this scale will always present operational challenges and we are delighted to have delivered this critical piece of infrastructure safely, on time, on budget and with minimal impact on airfield operations or our neighbouring communities.

“Now, after more than 18 months of meticulous planning and execution, LLA has a new runway in peak condition to ensure a safe, simple and friendly passenger experience for the millions of travellers who pass through the airport each year.”

The programme of works included a taxiway extension, the replacement of over 1,000 halogen runway lights with more energy-efficient LED units, and the installation of a new weather sensor for enhanced forecasting accuracy.