BRISBANE AIRPORT’S NEW RUNWAY A STEP CLOSER TO COMPLETION
Share
The construction of Brisbane Airport’s new runway has reached a critical milestone, with the application of asphalt – the final layer of the runway’s pavement – commencing today.
Over the next three months, more than 100,000 tonnes of aircraft-grade asphalt will be placed on top of the runway’s 2.5 metres of compacted sand and 600-milimetre layer of fine crushed rock.
Fulton Hogan has been sub-contracted by Skyway to produce a specially-designed asphalt on site that allows flexibility, load-spreading capacity, deformation resistance and the ability to withstand aircraft-induced shear stresses and high temperatures.
Project director, Paul Coughlan, says: “Given that site preparation and reclamation works for the new runway commenced way back in July 2012, it is incredibly exciting to be reaching a point where the end of construction is now in sight.”
Graeme Fenemore, Skyway joint venture project director, said the milestone is representative of the significant progress made to date which has been the culmination of an open and collaborative relationship between Skyway and BAC.
“Together we have implemented innovative engineering solutions while always putting the safety of our workforce first, proudly recording in excess of 2.2 million hours with an outstanding safety record.
“By continuing the momentum we have, I am confident the project will be delivered safely to the satisfaction of the wider community.”
Skyway, a joint venture (JV) between BMD Constructions Pty Ltd and CPB Contractors Pty Ltd, was awarded the Airfield Works contract in July 2017, and with around 12 months of construction to go, they have:
- Airfield conduits and pits 90% complete.
- Modified fine crushed rock (taxiway pavement base course) 80% complete.
- Taxiway concrete (final taxiway pavement layer) more than 50% complete.
Following the completion of the construction programme, the detailed commissioning process for the new ground lighting, navigational aids and control tower systems will commence.
Brisbane’s new runway remains on track to be operational in mid-2020.